1. Draft Cash to Year-end 2025 (incl summary YTD April I/E)
The CFO provided an update to the Committee in relation to the draft Cash to Year-end 2025 (including summary YTD April I/E), which describes a foreseen overspend of €517m (excluding demand led schemes and excluding disability services) which is the mid-point of two forecasts. He advised that the higher of which assumes the same level of growth in cash utilisation in May to December as the average of the last 4 years (the range between the two forecasts is from €407m to €627m). The CFO advised that it may be reasonable to characterise the deficit as largely related to an inability to deliver sufficient savings rather than a lack of control over costs however the level of growth outside run rates currently forecast in our Q1 I/ E projections needs to be reduced if that is to continue to be reasonable characterization.
2. Summary consolidated report on YTD April Savings
The CFO provided and update to the Committee and presented a first draft summary consolidated report on YTD April Savings against initial regional and national savings plans at 30 May 2025, which covered YTD April reporting against initial 2025 savings plans - Pay including Agency plus Non pay & Income; Procurement contracts and net savings from same; Energy Savings; and Consultancy / Contractor savings.
The Committee noted subject to various caveats, reporting plans are in place with a total €138.6m of savings targeted delivery for 2025.
The Committee discussed the need for further reductions in consultancy costs, travel and postage savings and requested that a more detailed report be brought back to the July meeting which outlines a set of initiatives, savings and how they are being tracked.
3. Expenditure Approval Limits
The CFO provided the Committee with a draft proposal to amend the NFR non pay expenditure thresholds for their consideration, which follows the previous paper presented at the April meeting. It was noted that the aim is to improve the quality of non-pay expenditure approval decisions by involving more senior managers, who are typically budget holders or closely support budget holders, more directly in the process.
An outline was presented in the paper, based on the consideration of data from the IFMS ledger for the first quarter of 2024, and an outline of potential risks and opportunities arising from each of the four proposals (P1 – P4) were presented.
The CFO suggested to the Committee that a hybrid of proposals P3 and P4 should be chosen, and that a further analysis is required to assess and align the PO volumes and spend Value % to the final suggested threshold as outlined in the paper.
The Committee considered the proposal as presented and agreed with the CFO suggestion of hybrid of P3 and P4, and outlined that an associated metrics report would be required. The Committee welcomed the revision to the expenditure approval thresholds as set out in the paper, noting that this will improve control of non-pay expenditure.
4. Health Budget Oversight Group (HBOG)
The Committee noted the minutes of HBOG meetings of 23 January 2025 and 22 February 2025.
5. National Service Plan 2026: Estimates
The Committee noted the paper presented and the overall approach to budgetary planning including both Existing Levels of Service (ELS) and New Service Developments (NSDs) for 2026 and 2027, and noted that the Estimates for Disability Services will be managed through a parallel process. The Committee noted the priority areas and approach adopted, and that the total early view requirements are: 2026 - 3,345 WTEs, full year cost €479.12m and 2027 - 1,375 WTEs and full year cost €144.99m, which were submitted to the Department of Health on 04 June 2025.
6. Integrated Financial Management and Procurement System (IFMS) update
Valerie Plan, Asst CFO joined the meeting
An update was presented to the Committee by the CFO in relation to the IFMS Accelerated Plan which was approved by programme governance on the 29 February 2024. The Committee noted that following the implementation of IFMS in Implementation Group 1, full deployment of IFMS across the HSE (statutory) is underway in two remaining implementation groups (IG2 and IG3). Upon completion of IFMS deployment to the HSE, approximately 80% of all health expenditure will be transacted on IFMS. The CFO advised that under Phase 2, for which planning has commenced, IFMS will be rolled out to all voluntary organisations in scope, i.e. all Section 38 organisations, and Section 39 Voluntary Organisations in receipt of annual funding in excess of €10m. The Committee highlighted the need to closely monitor the roll out of IFMS to voluntary organisations.
7. Contract Approval Requests
The CFO and ND Procurement presented to the Committee the following Contract Approval Requests (CARs).
- Award of contract for the Supply & Delivery of 6 in 1 Vaccines
- Award of contract for the Supply & Delivery of a Monoclonal Antibody for Respiratory Syncytial Virus (RSV) Passive Immunisation for Pathfinder Programme 2
The Committee considered the details of the proposed CARs and agreed to recommend to the Board for approval.