8.6 Contract Approval Requests
The CFO presented to the Committee the following Contract Approval Request (CAR).
- Contract Approval Request (CAR) for the OGP Tender on behalf of HSE/Health Sector for the Provision of Natural Gas Supply
In response to questions from the Committee in relation to the use of savings made being used to reduce energy demands, and if a claim can be made on the Windfall tax on energy, the CFO provided an update in relation to the use of savings and agreed to follow up and forward a response to the Committee in relation to windfall tax.
8.2 YTD Expenditure including Letters of Determination
The CFO advised the Committee that there was no paper to present in relation to the YTD Financial Position. He advised that the Fórsa dispute had been suspended, and that work is currently underway in relation to collating the reports for September - December 2023. It was agreed with the DoH and DPER that one overall commentary for the final 4 months would be available mid March. The Committee noted that the January 2024 report will then be finalised and available end March, after which the February reporting cycle will return to normal.
8.3 Health Budget Oversight Group (HBOG)
The CFO advised that a meeting with HBOG took place the previous week.
8.5 IFMS Update
V Plant, Asst CFO joined the meeting
The CFO provided the Committee with an update in relation to IFMS, which went live on time and as planned with the first of five Implementation Groups on 1 July 2023. While preparations and replanning for IG2 were underway, he advised that two material developments occurred in early October 2023, which included the commencement of the Fórsa Industrial Action, and the DoH providing additional funding of €40m in the HSE’s 2024 Letter of Determination, for the purpose of accelerating the rollout of IFMS. These two developments necessitated a new re-plan on the basis of an accelerated implementation schedule, with agreement of an associated change to the System Integrator contract.
He advised that the final detailed IFMS accelerated implementation plan is due for submission to programme governance on 29 February in preparation for commencement immediately in light of the recent resolution of the industrial action.
The Chair requested that the Committee be kept updated in relation to IFMS, and noted that quarterly reports are submitted to the Technology & Transformation Committee.
V Plant, Asst CFO left the meeting
8.1 AFS Significant Issues and Judgements
The Committee noted the briefing paper circulated, outlining the statutory and regulatory background to the production of the Annual Financial Statements (AFS), the associated timelines and an overview of any issues which may have a material impact on same. The Asst CFO advised the Committee that the production of the draft AFS in accordance with the DPER requirements is on track but also outlined a number of possible issues that could impact on this. The paper provided an overview of key issues impacting on the production and Audit of AFS 2023 and the key issues that have arisen in the past 2 years that are reflected in the Statement of Internal Controls and/or Audit Certificate only.
The Committee discussed the current significant issues and judgements impacting AFS 2023 relating to IFMS, private insurance, and the Vaccine Write off and Provision 2023 and asked how many vaccines were included in the write off, the possibility of vaccine donation and the cost implications of disposal of vaccines. The CFO provided an update in relation to vaccine donation and a response would be made available to the outstanding questions.
The Committee noted that the final draft AFS would be brought to the March meeting for recommendation to the Board.
8.4 2023 Review of Effectiveness of Systems of Internal Control within the HSE - Controls Assurance Review Process
M Percy, General Manager, Finance Governance and Compliance joined the meeting
The Committee were presented with an update in relation to the 2023 Controls Assurance Review Process (CARP) by the General Manager Governance & Compliance. The Committee were advised that 4,220 staff and senior management completed the CARP, an increase of 18% participation on 2022, and that participation levels of clinical staff had increased.
She advised that a National Training Plan was completed prior to CARP which saw a significant increase in attendance with 1,146 staff attending webinars whilst others accessing online versions and supporting documentation. The Committee noted that ASM, the external audit firm have completed their validation review of the Internal Controls Questionnaire responses of 261 staff who were audited and a finalised report was presented to Governance and Compliance on 9th February 2024.
The Committee discussed the three high priority findings in the areas of Absence of a National Financial System, Procurement, Payroll & HR controls, and it was noted that the medium priority finding in the area of ICT Control Environment and Grants to outside agencies have moved from High to Medium given the level of process developments and control enhancements implemented during 2023 and based on review and assessment of audit and CARP findings throughout the year.
The Committee noted that the review of effectiveness of the system of internal control is a key requirement of the HSE’s Code of Governance and forms part of the Statement of Internal Controls (SIC) report, which is currently being drafted and will be provided to the C&AG as part of the DPER Code requirement.
M Percy, General Manager and M Dolan, Asst CFO left the meeting