Brian O’Connell, ND, Head Strategic Health Infrastructure & Capital Delivery (ND SHICD) joined the meeting.
7.1 Regional analysis of distribution of projects
The National Director for Strategic Health Infrastructure and Capital Delivery (ND SHICD) provided the Committee with an update in relation to the capital investment over the past 6 years in both Health (approx. 6.14bn) and Disability (€90m) overarching care groups across Health Regions, which covers both major and minor capital funding categories and a full range of programmes with approximately 409 major capital projects completed in Health and approximately 77 major capital projects completed in Disabilities.
The Committee noted per region the number of major capital projects completed; health and disability expenditure; and the national expenditure between 2020 and 2025.
The Committee discussed with the ND SHICD reasoning why Public Private Partnership (PPP) expenditure is reported nationally rather than regionally, noting that PPP projects are funded through a centrally managed national contract and budget, although facilities are located across regions. And in relation to the disability capital investment in the context of regional disability needs, it was noted that work is underway to assess future service demand and inform investment planning.
7.2 Provision of community beds for older persons (in relation to closing out HIQA replacement programme)
The ND SHICD provided the Committee with an update in relation to the provision of community beds for older persons, noting that an infrastructure programme was established in 2016 to provide works to originally envisaged 90 Residential Care Centres,(currently 95 projects, as a result of phasing and sequencing) inclusive of 10 No. units originally planned to be delivered via a PPP (reduced to 7) The Committee noted the current programme status, with 78% at tender/construction stage or complete, a further 13% at design stage, and expenditure to date amounting to €622m with future expenditure estimated to be of a similar scale to complete the programme.
In response to the Committee’s query on completion, ND SHICD advised that the programme is expected to conclude but is unlikely to achieve 100% delivery, as some projects, are no longer expected to proceed. A paper will be brought forward outlining the final position, with delivery currently estimated at approximately 91% of the original programme and decisions on remaining projects to be finalised over the next 12–24 months.
7.3 Quarterly Report - final account for completed construction projects – verbal update
ND SHICD provided a verbal update confirming that there are no final accounts agreed for Q1 2026 for completed construction projects.
7.4 Update on Property Disposals
The ND SHICD provided an update to the Committee of the progress made under the accelerated disposal programme implemented in 2025 to streamline the release of surplus or underutilised properties during 2025 and Q1 2026, which included the current portfolio position. The Committee noted 142 buildings deemed surplus to HSE requirements as at end of Q1 2026; the composition of the current disposal pipeline; the ongoing prioritisation of complex and strategic campus site disposals; and the key risks to delivery, including legal, planning and title complexities.
The Committee discussed the need to ensure that value generated through Land Development Agency transfers is recognised and queried whether stronger alignment could be achieved with the ND SHICD and CFO to reflect savings delivered to the State, noting that capital and revenue budgets are treated separately but it was agreed that the ND SHICD would follow up with the CFO to explore any potential opportunities.
The Committee discussed the key focus for 2026 of the progression of the disposal of major campus sites, and discussed Residential Zoned Land Tax, and the possibility of retrospective recovery under the legislation, including following disposal of a site, and agreed that clarification would be sought.
7.5 Building Contracts & Properties
The Committee considered the details of the following proposed contracts which was presented by the ND SHICD.
The Committee agreed to recommend to the Board for approval the following contracts:
- Contract Award for construction of a 3 Storey extension to the Corduff Primary Care Centre for the Enhanced Community Care Programme
- Proposed extension of lease of Primary Care Centre at Youghal, Co. Cork to provide a Permanent National Ambulance Service Training College