Patrick Lynch, National Director Planning & Performance; Brian O’Connell, Interim ND Capital & Estates; Dr Philip Crowley, ND Wellbeing, Equality, Climate and Global joined the meeting
6.1 Climate Strategy - Update on progress
The ND Wellbeing, Equality, Climate and Global (ND WECG) provided to the Committee an update on progress on the HSE Climate Action Strategy Implementation (Strategy), which sets out the HSE’s commitment to deliver net-zero emissions no later than 2050, and delivering healthcare that is environmentally and socially sustainable. The Strategy outlines the HSE’s approach to addressing the Government’s National Climate Action Plan (NCAP).
The Committee also noted the HSE’s Infrastructure Decarbonisation Roadmap, which sets out an approach and actions to achieve the Energy targets set out in the NACP to deliver an estate that is Net Zero by 2050, which is managed by the HSE Capital and Estates team and has been updated for 2024 and submitted to Sustainable Energy Authority of Ireland (SEAI).
He outlined that ten strategic objectives, under six priority areas, and two additional enabling functions have been identified as the building blocks of the Strategy. A Steering Group has been appointed and working groups are in place to coordinate implementation of each of the ten objectives.
As highlighted in the paper, he outlined the key achievements to date, and advised the Committee of the plan to hold an in-person Sustainability Leadership course, which will be delivered by Change by Degrees in Q3 2024 for the HSE Leadership Team and Board members, to which ARC members were welcome to attend.
The Committee held a discussion in relation to the importance of the implementation of Green Public Procurement; that no standardised process exists for Fleet Management across the HSE; and the mapping of health services facilities in relation to flood risk.
The Committee welcomed the positive progress since the launch of the Strategy in June 2023, and noted that Climate Action is a core priority for implementation of the HSE. It was agreed that further updates would be brought to ARC on a half yearly basis.
ND WECG left the meeting
6.2 National Children’s Hospital (NCH) Project and Programme Update
The ND Planning and Performance (ND P&P) provided an update to the Committee in relation to the National Children’s Hospital (NCH) Project and Programme.
At the request of the Committee at the June meeting, the ND P&P provided the Committee with a copy of the Operational Readiness Review which was commissioned by him as the HSE Lead Director, and undertaken by an international expert, Professor Melvin Samsom, which has concluded. The final Report and Implementation Plan was approved by the CHI Board, and the CHI are responsible for implementing the plan, which will be monitored through the HSE Lead Director process.
- The Committee noted the key actions to give effect to the Report’s recommendations, which were Transformation; Operational Leadership; Clinical Leadership; The Organisational Model; and Managing the Programme. Professor Samson in making these recommendations stated that ‘These recommendations should be seen as a package that require implementation in a timely manner to reduce the risks of failed commissioning / transformation programme’.
The Committee were advised that the CHI have undertaken detailed planning on the operational commissioning programme and submitted a paper to the HSE in June 2024, and is now under review. The CHI commissioning team has been strengthened with the recent approval by the HSE of a further 36 CHI commissioning posts. The HSE continues to monitor CHI’s implementation of its wider workforce plan, through the established ‘Quarterly Workforce Review’ process.
The Committee discussed the external assurance review and Implementation Plan, and highlighted their concern in relation to some of the serious issues and risks to the programme, and with the CHI’s ability to deliver on this next phase, which could result in further timescale delays, additional costs, safety and quality issues and reputational damage for CHI and HSE.
In relation to the programme management and programme oversight arrangements, in which the HSE has responsibility for programme funding and assurance, the Committee outlined the importance of oversight by the HSE Board.
6.3 National Maternity Hospital
The ND P&P provided an update to the Committee in relation to the National Maternity Hospital (NMH) at St. Vincent’s University Hospital (SVUH) Programme – Governance and Resource Mobilisation.
The Committee noted that the Programme Governance Structure for the NMH at SVUH Programme was previously presented to the Committee in November 2023, where Option 2, which proposed HSE as the Contracting Authority and primary delivery entity, as the preferred option to ensure that effective and clear governance arrangements are in place to deliver the programme, was endorsed, approved by the Board and had subsequently been reviewed and feedback received from the DoH, NMH and SVUH.
The ND P&P advised that the Programme is now at a critical juncture with multiple work streams ongoing in preparation for approval to award the main construction contract and to ensure readiness to commence these works on site. The mobilisation of the Programme Governance Structure, and of the associated resources required, is a key priority for the Programme. Approval by the NMH of the Programme Governance Structure remains outstanding, and is a dependency for progressing mobilisation.
The Committee noted the summary of the key milestone timelines for the governance and resource mobilisation.
The Committee discussed the Programme Reporting Lines under the Programme Governance Structure, noting the responsibilities of the HSE.
The Committee discussed the key lessons learned from the NCH in relation to the timely mobilisation of the Programme Governance Structure, and that the HSE must deliver this programme to timescale, to budget and to quality and safety standards, and outlined that the HSE Board will need to establish its own robust governance mechanisms to complement those built into the programme structure.
6.4 Capital & Estates Strategy - Update on progress
The Committee noted the update on progress in relation to the Capital & Estates Strategy, essential enabler to providing the healthcare infrastructure to support current and future service needs.
The Committee were advised that work is ongoing with the DoH towards the publication of the Strategic Healthcare Investment Framework (SHIF), which is expected for publication in the coming weeks. Work is also ongoing with the DoH to develop the Common Appraisal Framework (CAF) to implement the SHIF, a key objective of which is to develop a CAF to address the need for consistency of approach in planning and decision making in relation to capital investment proposals.
The Committee noted the update in relation to the recruitment process for the National Director for Capital & Infrastructure, which will build capability at national level for both the planning and implementation of major infrastructure projects.
It was agreed that a further discussion in relation to the Capital & Estates Strategy would be brought to the September meeting.
6.5 Quarterly Report on relevant Property transactions delegated to the Executive
The Interim ND Capital & Estates provided a summary report on transactions approved between €2m & €10m and low value/nominal CAT 3a transactions for the period of 01 April – 30 June 2024, which was noted by the Committee.
6.6 Building Contracts and Properties
The ND P&P and Interim ND Capital & Estates presented the following proposed contract to the Committee, who considered with close scrutiny the detail, and agreed to recommend to the Board for approval.
Interim ND Capital & Estates left the meeting